What was recommended to the company and the benefit expected from each. These are proposals; the report does not measure results after implementation.
| Recommendation | Step | Addresses | Expected benefit | Effort |
|---|
On hand ÷ average daily demand, for each finished-goods item. Colour shows the item's status.
Open order quantity by the week of its On Time Ship date, split into what available stock covers and what must be built.
| Item | Description | On hand | On order | 30-day demand | Safety stock | Reorder point | Days on hand | Suggested build | Comment |
|---|
Ranked by OTS date, then ESD. Stock is allocated to the earliest lines first.
| # | Order | Line | Item | Qty | From stock | Short | OTS | ESD | Timing | Comment |
|---|
Test strips move from raw material procurement through reagent preparation, manufacturing (soak, dry, slit, prepare, final slit), quality control and packaging to shipping. Production planning schedules this flow.
MTO Made to Order · MTS Made to Stock · OTS On Time Ship · ESD Earliest Ship Date · FG Finished Good · BOM Bill of Materials · WO Work Order
Process maps and findings from the project report. The Stock Needed Report tab uses sample data generated by prototype/src/make_sample_data.py.